179. Fill for Darwin Port Expansion

Ms Purick to MINISTER for Lands and Planning

QUESTION

    1. When the port is expanded in accordance with current plans, how much fill will be required and from where will it be sourced.

ANSWER


Answered on 10/08/2010
LEGISLATIVE ASSEMBLY OF THE NORTHERN TERRITORY

WRITTEN QUESTION

Ms Purick to Minister for Lands and Planning
Fill for Darwin Port Expansion

1. When the port is expanded in accordance with current plans, how much fill will be required and where will it be sourced from.
___________________________


ANSWER

The Darwin Port Corporation has two current reclamation projects – the Eastern Reclaim Area, which is being filled and surcharged to provide additional hard stand and cargo lay down area, and the filling of Pond F which is located behind the main wharf and will be used to provide additional covered cargo storage areas.

Reclamation projects are managed on behalf of the Corporation by the Department of Construction and Infrastructure, who have a panel contract for the provision and supply of fill.

The Panel Contractors will be supplying naturally occurring terrestrial fill from their own private borrow pits and quarries located around the Greater Darwin Area. The Eastern Reclamation Area requires about 150,000m3 of earth fill and Pond F requires about 100,000m3 of earth-rock fill and about 200,000m3 of earth fill.
Last updated: 04 Aug 2016