Darwin City Waterfront - Lock
w
WRITTEN QUESTIONS
10th Assembly
19/07/2005
6. Darwin City Waterfront - Lock
Ms Carney to MINISTER for Infrastructure and Transport
QUESTION
1. Why isn’t the lock included in the Community Infrastructure?
2. What guarantees are that the consortium will build the lock at a later stage?
ANSWER
Answered on 05/10/2005
I:\COMMUNICATIONS & MARKETING\Cabinet\Written Questions\August 2005\M20050362TI - Written Question 06.doc
Q1 The lock is not needed until stage 2 is underway.
Q2 The lock is a required component of the Stage 2 infrastructure under the terms of the Residential Project Delivery Deed.
WRITTEN QUESTIONS
10th Assembly
19/07/2005
6. Darwin City Waterfront - Lock
Ms Carney to MINISTER for Infrastructure and Transport
QUESTION
Darwin City Waterfront - Lock
1. Why isn’t the lock included in the Community Infrastructure?
2. What guarantees are that the consortium will build the lock at a later stage?
ANSWER
Answered on 05/10/2005
I:\COMMUNICATIONS & MARKETING\Cabinet\Written Questions\August 2005\M20050362TI - Written Question 06.doc
Q1 The lock is not needed until stage 2 is underway.
- The lock is not included in the Community Infrastructure because it is being provided and paid for by the Private Sector. The lock infrastructure may be built as part of stage 1 at the option of the Stage 2 developer.
Q2 The lock is a required component of the Stage 2 infrastructure under the terms of the Residential Project Delivery Deed.