154. Roundabout at Lambrick Avenue/Chung Wah Terrace

Mr Wood to MINISTER for Transport and Infrastructure


Hide details for QUESTIONQUESTION
1. There was a contract let during 2003/04 for a roundabout at the corner of Lambrick Avenue and Chung Wah Terrace, how – (d) much did the job finally cost the government.

Hide details for ANSWERANSWER

Answered on 20/08/2004


(a) The contract took 38 weeks to complete. A Certificate of Practical Completion was issued on 12 July 2004.

(b) The initial contract period was for 10 weeks.

(c) The original contract price was $712 727.55.

(d) The final contract price was $998 745.72.


Both contract costs and times were adversely affected by the unexpected location of high voltage underground cables.