1. There was a contract let during 2003/04 for providing lighting at the corner of Howard Springs Road and the Stuart Highway –
Hide details for ANSWERANSWER

Answered on 20/08/2004


(a) The contract took 19 weeks to complete. A Certificate of Practical Completion was issued on 29 January 2004.

(b) The initial contract period was for 15 weeks.

(c) The original contract price was $172 410.55.

(d) The final contract price was $192 406.24. The increase was partly due to a misdiagnosed street lighting fault.