Department of the Legislative Assembly, Northern Territory Government

Greatorex Electorate Office

1. What was the successfully tendered cost estimate to renovate the Electorate Office for the Member for Greatorex.

2. What was the final cost of renovating the Electorate Office for the Member for Greatorex.

3. What was the reason for any variation between the tendered cost and the final cost of completion for the renovations to the Greatorex Electorate Office.

ANSWER

1. (a) Successful tender for work funded by the Department of the Legislative Assembly was $13,436.00;

(b) Work undertaken for, and funded by, the owner of the building, Yeperenye Shopping Centre, was done at a cost of $12,580.00.

2. $26,016.00.

3. Renovation work was funded and carried out in two parts - i.e. -

PART A - Government funded - $13,436.00 final cost;

PART B - Funded by building owner - $12,580.00.
Last updated: 04 Aug 2016