Water to LNG plant, Wickham Point
WRITTEN QUESTIONS
9th Assembly
16/07/2004
156. Water to LNG plant, Wickham Point
Mr Wood to MINISTER for Lands and Planning
QUESTION1. What was the final cost of supplying water to the LNG plant at Wickham Point.
2. What money did CononcoPhillips provide towards getting water.
ANSWER
Answered on 07/10/2004
G:\DATA\LA\EXEC\CLRK_ASS\Wqst9ass\Wqstsans\Aqsts156.doc
1. The water supply to Middle Arm is designed to supply future customers additional to the LNG plant. The cost of providing Middle Arm water supply was as follows
Stage A $1 555 129.01
Stage B 2 713 947.42
Stage C 1 870 652.31
Stage D 896 153.91
$7 035 882.65
2.Darwin LNG Pty Ltd pays the standard tariffs (fixed and variable components) for the water supply at metered supply points.
Last updated: 04 Aug 2016